You can't make this stuff up. Mobilitie allegedly erected a new mini-macro tower in Goliad, TX – which we posted about on LinkedIn previously. Subsequent to that, this story regarding Sprint approving a trial for Mobilitie to build mini-macro small cell towers without full regulatory compliance is found by reporters at Event-Driven.
In this case, Mobilitie claimed to the County they had all permits. City officials from Goliad investigate and find that Mobilitie did not build the tower in County limits but in the City. City officials then demand that Mobilitie remove the tower or they will do it for them. Mobilitie claims that they needed 2 weeks to do so- to which the City replied
“your firm constructed the tower over a two-day period, on a weekend. Surely, if you could install the tower in two days, you can dismantle it in the same time period.”
Not only did Mobilitie fail to build the tower outside City limits, they may have even failed to build it straight. As reported in the Goliad Advance-Guard, local homeowner
Harvey also claimed the tower is leaning to the north. Blueprints for the installation require a foundation 31 feet deep into the ground; Harvey who says he has had years of experience mounting poles, says a driller will hit bedrock at the 10-foot level.
County officials claim that this type of overnight tower erection was happening in other areas. See the quote below from the Advance-Guard.
“And it’s not just our community, it’s happening in San Patricio County as well,” City Alderman Nathan Lill told the group. “There’s list of other counties that have had the same issue with this exact same company. They’re building the towers at night and they’re not asking permission from anybody to do it.”
This isn't the only place where Mobilitie has been either fined or forced to remove what is alleged to be an improperly permitted tower- it has occurred in Baltimore, MD, and Denison, TX.